Building Progress Update January 2012

PROGRESS REPORT
DECEMBER 21 – JANUARY 17


Elementary – Junior High School Renovation
La Harpe CUSD NO. 347
La Harpe, IL 61450
Construction Schedule: May 23rd – September 30th
PROJECT NO.: 11006


Work done:
1. The work is substantially complete and the occupancy has been given to the school. The
punchlists have been given to the contractors in which most of the items have been addressed.
Work taking place:
1. Masonry – Punchlist – Evans – Mason - Addressed
2. General Work - Punchlist- Schlipman - Addressed
3. Flooring – Punchlist – Moore’s - Addressed
4. Roofing – Certification and punchlist. Geissler Roofing - Addressing
5. Windows – Punchlist. – Leander - Addressing
6. Plumbing – Punchlist – Vinson and Sill - Addressed
7. Mechanical – Punchlist. – Peters H & A - Addressing
8. Electrical – Gym lighting. Punchlist. – Jansen - Addressed
9. Sprinkler – Punchlist. – Automatic - Addressed
10. Stud & drywall – Punchlist. Schlipman. - Addressed
Work to come:
1. General Work – Signage.
2. Plumbing – Final inspection
3. Mechanical – Instruction to maintenance/staff.
4. Electrical – Gym lights.